concrete weight coated pipe coating process,cwc pipe coating process

Concrete weight coated pipe coating process

Date:2024-10-16

Concrete weight coating (CWC) is a method used to apply a dense concrete layer over a pipe, primarily to provide negative buoyancy and protect the pipe in offshore or underwater environments. This process enhances the durability of pipelines by offering mechanical protection and corrosion resistance while also helping to ensure the pipe remains submerged in subsea applications. The following is a detailed guide on the concrete weight coating process.

 

1. Surface Preparation

Before the concrete coating is applied, it is essential to properly prepare the pipe's surface to ensure strong adhesion and coating durability.

 

Pipe Cleaning: The steel pipe surface must be cleaned to remove any dirt, oil, grease, rust, or other contaminants. This is typically done through methods like sandblasting or grit blasting to achieve a clean, rough surface (surface profile) for better bonding.

 

Corrosion Coating Application: A corrosion protection layer, such as Fusion Bonded Epoxy (FBE), polyethylene, or a 3-layer polyolefin system, is applied to the cleaned steel surface. This layer serves as the primary corrosion barrier, protecting the pipe from exposure to corrosive environments. The corrosion coating is cured and checked for defects or holidays (areas where the coating is absent).

 

2. Welding and Joint Preparation

The ends of the pipes (typically 150 mm or 6 inches) are left bare (without the corrosion coating) for welding purposes. After the pipes are welded together, the joint areas are coated separately using field-applied coating materials to ensure a continuous protective layer.

Field Joint Coating: Once the field welds are complete, field joint coatings, such as heat-shrink sleeves or liquid epoxy, are applied to the weld zone to ensure the corrosion coating is continuous along the pipeline.

 

3. Concrete Weight Coating Application

The concrete coating process typically involves applying a dense concrete layer to the pipe to provide negative buoyancy and mechanical protection. The application process can vary slightly depending on the type of concrete coating used (e.g., impingement or compression coating), but the basic steps are as follows:

 

Steel Reinforcement (Optional): Some concrete-coated pipes include steel wire reinforcement to improve the mechanical strength of the concrete. Steel mesh or rebar cages are placed around the pipe to provide additional support and prevent cracking.

 

Application of Concrete Mixture: The concrete weight coating is applied in a controlled environment, typically using automated equipment. The concrete mix consists of cement, aggregates (such as gravel or sand), and water, with the inclusion of additives to enhance strength, density, and workability. The mixture is formulated to provide the necessary weight and mechanical protection for the pipe.

 

Coating Method:

Compression Coating: In this method, concrete is pressed onto the pipe's surface as it rotates, ensuring even coverage. This method is common in onshore coating facilities.

Impingement Coating: Concrete is sprayed onto the rotating pipe, layer by layer, using specialized nozzles. Impingement coating is more commonly used in offshore pipelines, where additional coating thickness and weight are often required.

 

Vibration and Compacting: After the concrete is applied, vibration or compacting tools are used to ensure the concrete is evenly distributed around the pipe, with no voids or air pockets. Proper compaction is critical to achieving the desired density and strength of the concrete coating.

 

Thickness Control: The thickness of the concrete layer is monitored throughout the process to meet the design specifications. The typical thickness ranges from 40 mm to 150 mm, depending on the pipe’s size and the specific requirements of the project.

 

4. Curing and Hardening

Once the concrete is applied, it needs time to cure and harden. Proper curing is essential to ensure that the concrete reaches its intended strength and durability.

 

Curing Process: The coated pipes are placed in a controlled environment for a specific period, allowing the concrete to set and harden. During this phase, the concrete’s chemical reaction with water (hydration) continues, and the pipe must be kept at the appropriate humidity and temperature levels to prevent cracking or weakening of the concrete.

 

Post-Curing Inspection: After curing, the concrete coating is inspected for uniformity, cracks, and other potential defects. The coating thickness is checked again to confirm it meets the project’s specifications. Any damaged areas are repaired as necessary.

 

5. Quality Control and Testing

Several tests are performed to ensure the concrete weight coating adheres to quality standards and project requirements:

 

Thickness Measurement: The thickness of the concrete coating is measured at various points to ensure uniformity and compliance with design specifications.

 

Density Testing: The density of the concrete coating is tested to confirm that it provides the necessary weight to achieve the required buoyancy control.

 

Adhesion Test: Adhesion tests may be conducted to ensure the concrete coating is firmly bonded to the corrosion protection layer beneath it.

 

Impact Resistance: The coating is tested for impact resistance to ensure it can withstand mechanical stresses during transportation and installation.

 

6. Handling, Storage, and Transportation

Once the coating process is complete, the pipes are prepared for storage or transportation to the installation site.

 

Handling: Coated pipes are handled using padded slings or other protective equipment to avoid damaging the concrete. Careful handling is critical to maintaining the integrity of the coating.

 

Storage: If the pipes are stored for extended periods, they must be kept in a secure and stable environment, ensuring that no external pressure or weight is placed on the coating.

 

Transportation: During transportation, the pipes are loaded and secured properly to prevent movement, impact, or abrasion, which could damage the concrete coating. Specialized cradles or racks are used to protect the coated pipes during transit.

 

7. Installation

The installation of concrete-coated pipes, whether onshore or offshore, requires specialized equipment to handle the heavy weight of the pipes. Techniques such as trenching (for onshore) or laying (for subsea pipelines) are employed with extra care taken to prevent damage to the concrete coating during placement.