concrete coated pipe installation guide,cwc pipe installation guide

Concrete coated pipe installation guide

Date:2024-10-16

Concrete coated pipes are commonly used in environments where additional protection is needed against external corrosion, mechanical damage, and other harsh conditions. These pipes are often employed in offshore and underwater pipelines due to their durability and weight, which helps them stay submerged. Proper installation of concrete coated pipes is essential to ensure their long-term performance. Below is a step-by-step guide on the installation process.

 

1. Pre-Installation Preparations

Site Survey: Before installation, conduct a thorough site survey to identify any potential hazards, access routes, and equipment requirements. Make sure the area is cleared of debris and obstacles.

Pipe Inspection: Inspect each concrete coated pipe for any visible damage, including cracks or chips in the coating, and ensure the concrete is evenly distributed. Check the pipe ends to confirm that they are beveled and meet the specified requirements for welding.

Material Handling: Use appropriate lifting tools, such as slings or padded clamps, to handle the pipes without damaging the concrete coating. Avoid dragging or dropping the pipes to prevent chipping or cracking the protective layer.

 

2. Trench Preparation (for buried installations)

Excavation: Dig the trench according to the pipeline design specifications, ensuring the depth and width allow for proper bedding and spacing. The trench should accommodate the size of the pipe and the required cover depth.

Bedding: Lay a layer of compacted sand or soft fill material at the bottom of the trench to provide a stable base for the pipe. The bedding should be uniform to prevent stress points on the pipe and its coating.

 

3. Pipe Alignment and Joining

Pipe Alignment: Align the pipes using positioning tools or alignment rollers. Proper alignment ensures that the pipes connect smoothly and reduces the risk of misalignment during welding or other joining processes.

Welding: Concrete coated pipes typically have bare steel ends for welding. Follow the welding procedure specifications (WPS) for the pipe material, ensuring a strong and reliable connection between each pipe section. After welding, inspect the welds for defects and carry out any necessary repairs.

Coating Repair: After welding, apply a coating to the welded joint area using an approved field-applied coating system, such as heat-shrink sleeves, tape wrap, or liquid epoxy. This ensures continuity of protection along the pipeline.

 

4. Lowering-In (for buried pipelines)

Lowering the Pipe: Once the pipes are joined and welded, lower them into the trench using cranes, side booms, or other heavy equipment with lifting straps. Take care to avoid damage to the concrete coating during this process.

Pipe Support: Ensure that the pipe is well supported by the bedding material in the trench. There should be no direct contact between the concrete-coated pipe and hard surfaces like rocks, as this can lead to damage over time.

 

5. Buoyancy Control (for underwater installations)

Weight Calculations: When installing concrete coated pipes underwater, calculate the buoyancy based on the water depth and pipe weight. The concrete coating provides weight that helps the pipe stay submerged, but additional measures like water-filled or sand-filled bags may be needed to prevent floating.

Submerging: Use controlled lowering techniques to submerge the pipe. Avoid sudden drops or excessive force when placing the pipe on the seafloor. Monitor the pipe’s position during the lowering process to ensure it is laid in the correct alignment.

 

6. Backfilling (for buried pipelines)

Initial Backfill: Begin backfilling with a layer of fine, compacted sand or soft fill material to a height of at least 150 mm (6 inches) above the pipe crown. This helps cushion the pipe and reduces the risk of damage to the concrete coating.

Final Backfill: Complete the backfilling process using soil or other appropriate material. Ensure the final backfill layer is properly compacted to prevent future soil erosion or trench collapse.

 

7. Testing and Commissioning

Pressure Testing: Once the pipes are installed and joined, perform hydrostatic pressure testing to ensure the pipeline is free of leaks and can handle the designated operating pressure. Check for any pressure loss during the test.

Inspection: Conduct a final visual inspection of the entire pipeline to ensure there are no visible defects or issues with the installation.

Commissioning: After testing, clean the pipeline of any debris or foreign materials and prepare it for operational use by gradually introducing the transported material (e.g., gas, oil, or water) into the pipeline.

 

8. Post-Installation Monitoring

Cathodic Protection: Install and activate the cathodic protection system to safeguard the steel pipe against corrosion in areas where the concrete coating may be insufficient or compromised.

Regular Inspections: Schedule regular inspections to monitor the condition of the pipeline, especially in areas where external factors (such as soil movement or environmental changes) might affect its stability.

 

Key Considerations

Safety: Always prioritize safety during the installation process, using appropriate protective gear, equipment, and procedures.

Environmental Factors: In underwater installations, be mindful of marine life and environmental regulations. Use eco-friendly practices when working in sensitive ecosystems.

Contractor Expertise: Work with experienced contractors and personnel familiar with the handling and installation of concrete coated pipes to ensure quality and safety standards are maintained throughout the project.

 

By following these steps and considerations, concrete coated pipes can be successfully installed with minimal risk of damage, ensuring long-term durability and effectiveness in a wide range of applications.